Snow Elementary was constructed in 1952 and sits on 13.6 acres of land.  

Under the 2026 transformational bond, the school would be completely remodeled.  Estimated remodeling cost $24,287,555.  Snow Elementary had air conditioning and new boilers installed a few years ago. For an overview, see the one-page Snow flyer.

An illustration showing when different parts of Snow Elementary were constructed including 1952 and 1955.

Phase 1 (Years one to five)

Phase 4 (Years 15 to 20)

  • Major renovations to classrooms, media center, and gym
  • Cafeteria and kitchen upgrades
  • Site improvements including parking and playgrounds
  • Major mechanical replacement
  • Building enclosure such as roofing, windows, doors
  • Major electrical replacement
  • Major plumbing replacement